How we schedule a 42-week build without the surprises

How we schedule a 42-week build without the surprises

A good schedule is not a wish list. It is a sequence of commitments, each with an owner, a lead time and a buffer.

Start from the handover date and work backwards

We fix the handover date first, then list the long-lead items that could threaten it: structural steel, glazing, switchgear and elevators. Those get ordered before almost everything else.

Break the build into stages

Our standard commercial build runs through five stages, each with a clear exit check.

  • Ground: Site preparation and excavation.
  • Foundation: Footings and slab poured and cured.
  • Frame: Structure and framing up.
  • Envelope: Roof, glazing and cladding sealed weathertight.
  • Handover: Final inspection and keys.

Build in buffer where it counts

Weather and inspections are the two most common sources of slip. We place float immediately before them, rather than spreading it thinly across the whole programme.

Report progress openly

Every client gets a weekly update showing percent complete, upcoming milestones and any risk to the date. Problems reported early are cheap, and the same problems reported late are not.

Conclusion

Predictable delivery comes from ordering early, staging clearly and being honest about risk. That is how we hold a 42-week programme to 42 weeks.